Posted on: August 8, 2023ROAD CORRECTION: Possible TxDOT Roadway Construction Delays on FM 2831 during construction.
ROAD CORRECTION: Possible TxDOT Roadway Construction Delays on FM 2831 during construction.
The City of HSB reached out to TxDOT on their construction project taking place on FM 2831 (Blue Lake Dr.). The following information was provided on the construction schedule dates for the for the project.
Schedule (weather permitting):
08/07 – 08/10 Full depth repairs
08/11 – 08/18 Level up overlay
08/21 – 08/22 Pavement edge repairs & level ups
08/23 – 08/24 WZ striping
09/13 – 09/13 Seal coat
09/14 – 09/31 final striping (not continuously, just the range)
The City Recycling Center will remain open normal hours, however due to FM 2831 construction there may be delays getting to the center.
This is a TxDOT roadway project. For questions or concerns, please contact TxDOT at 800-558-9368.